We are nearing the end of our women’s locker room remodel:

  • The fluctuation in hot/cold temperatures in the temporary showers is being fixed tonight
  • We are installing new shower heads in the family locker rooms to increase the water pressure
  • LED lighting in the main dry vanity was installed last week. The shadowing has disappeared. The brightness of the lighting will burn down slightly over the next couple weeks
  • We are pouring concrete for the whirlpool on Monday
  • Prep work for the tile was completed this week
  • We will begin laying tile tomorrow and all of next week
  • Plumbing for new drinking fountain has been completed
  • We are rebuilding the motor for the women’s steam room during the remodel