Men’s Locker Room Remodel Update – 9/15/2015

We are on the final stretch of the men’s locker room remodel! The estimated completion date is mid-October to early November and we hope to narrow that time frame shortly.

Updates:

  • The main dry vanity is in the demolition phase and will begin construction this week
  • Dry wall is complete
  • The whirlpool took 19 cubic yards of shotcrete to fill!
  • Sprinklers have been relocated and replaced
  • We are waiting on completion of the duct work to schedule inspection and close the ceiling
  • The next BIG milestone will be the start of tile work

Please remember, men have access to the women’s whirlpool/steam through Saturday, September 19. Access will return to women on Sunday, September 20. Thank you.

Men’s Locker Room Remodel Update 9/3/15

New completion date is scheduled for mid-October through early November. We anticipate decreasing the range as we progress with the project.

The main dry vanity is scheduled for demolition Monday, September 14 and will be closed for the remainder of the project. The lockers across from the dry vanity will still be available for use.

Important updates:

  • Drywall will start next week
  • The whirlpool shotcrete pour is scheduled for next Wednesday
  • All MEP inspections have gone according to plan
  • The next time the men will be able to use the women’s whirlpool/steam is Sunday, September 13 through Saturday, September 19

Thank you.